top of page
BMO.5.jpg

Projects

Construction Manager - Ledcor Group

Fabricators:
68th St Logistics – Knelsen Sand & Gravel

Point Trotter - Proform Concrete

68th Street Logistics & Point Trotter

Project Duration: February - October 2023

9620 68 St SE & 7121 108 Ave SE

 

The first project we started installation on here is the Rise at Point Trotter, which is comprised of two 105,000 sq footage warehouses that will be designated as commercial condominium bays.

 

Our second project in this area is the 68th Street Logistics Warehouses, these are open concept style warehouses designed for distribution and transport logistics.

Each building has approximately 350 precast wall panels that are strapped to the steel as a part of the building envelope and will take approximately 2-3 months for installation.

 

In total Con-Steel will be working in this area erecting four separate buildings and installing over 1200 precast concrete wall panels for a duration of approximately 10 months.

BMO Center Expansion

Project Duration: December 2021 - January 2024

20 Roundup Way SE Calgary

 

 At over one million square feet, the new BMO Centre will be the newest, largest, and most modern convention centre in Western Canada. Con-Steel installed 184 architectural brick inlay wall panels and 236 captones as part of this massive expansion project. Working in the downtown core was often challenging regarding site access and required a strategic plan. The installation of the grand staircase in particular  created some difficulties along the way and required a collaborative approach between the manufacturer, engineers and install team to meet the tight tolerances and acquire precise alignment.  This architecturally inspired building will accommodate and elevate major, year-round events and create memorable guest experiences.

Owner - Calgary Stampede

Construction Manager - PCL

Precast Fabricator - Knelsen Sand & Gravel

Amazon Violin Warehouse

& Distribution Centre

Project Duration: November 2021 - June 2022

68th St and 104 ave SE

 

At an impressive 1 million square feet, the Amazon Violin Warehouse & Distribution Centre located in SE Calgary is the largest project (square footage) that our crew has provided field installation services for to date. Over a period of 8 months we installed 666 load bearing precast concrete wall panels. This project required a 250 ton crane to lift the 55,000 lbs panels. Milestone scheduling was a top priority based on a tight timeline as we worked towards the owners targeted opening date. We were also responsible for international equipment procurement, resourcing bracing and screw anchors required for the install. As the scope of our work continues to expand we will continue to aspire to fulfill the wide range of our clients needs.

Owner - Amazon

Construction Manager - Clark Buidlers

Precast Fabricator: Knelsen Sand & Gravel

Owner - Telus

Construction Manager - Delnor Construction

Telus Len Werry Panel Removal

Project Duration: October 2022 - January 2023

7 Ave and 2 St SW Calgary

 

As the downtown Calgary skyline evolves and precast clad building envelopes have reached their lifecycle, Con-Steel is  here to manage and execute these removal and remediation projects.

Our team successfully removed 189 precast panels from the 15th to the 17th floor of the Telus Len Werry building over a bustling LRT station and where the panels were set under a cantilevered roof slab.

Our  team of experienced, skilled precast removal experts collaboratively worked with all contractors, engineers and required vendors to ensure the project was completed efficiently with the highest safety standards.

University Social Sciences Center

Project Duration: July - August 2022

University of Calgary

 

Completed ahead of schedule and with zero safety incidences, the Con-Steel crew was on site removing 478 precast panels at the University of Calgary Social Sciences Building Reclad Project.

 

Utilizing a 500 tonne Mammoet crane with a luffer jib the team worked off a swing stage at over 150 ft in the air and on night shift to ensure there was no disruptions to the day-to-day operations within this 14-storey building.

Owner - University of Calgary

Construction Manager - Ellis Don

Calgary Farmers Market

Building A & L

Project Duration: February – April 2021

Greenwich Village

 

Located in the Greenwich Village on the West side of Calgary, the new Calgary Farmers Market encompasses a unique building design and the architectural brick inlay panels will be sure to make this building stand out as a landmark project for years to come. A total of 220 insulated wall panels for Building A (brick inlay precast design) and 38 panels (architectural base) for Building L have been installed by Con-Steel.

 

Although, the building design and geometry modified the crews initial installation sequence, our talented and professional team ensured the project was completed on time and without any safety incidents.

Owner – Melcor Development

Construction Manager - Clark Builders

Precast Fabricator – Knelsen Precast

Learn more about the new Calgary Farmer’s Market and construction updates here.

"Con-Steel did an excellent job executing the lifts safety and working with our team to ensure the entire week went smoothly. The guys were helpful in planning the work each night and ensuring our lengthily list of restrictions were followed (Airport, traffic accommodation etc.). Your extensive knowledge on girders, bearings and hoisting is a huge benefit to the project."

Jon Stegman, Project Manager - PCL Construction

Airport Trail Bridge

Project Duration: February & April 2021

Airport Trail and 19 Street NE/Barlow Trail

 

Con-Steel has erected 18 NU precast girders over 2 spans at the Airport Trail and 19 Street NE intersection along with the installation of temporary bearings and steel diaphragms/bracing for one of two bridges without injury or incident.

 

Working through several night shifts and enduring some cold and snowy weather, our crew was able to complete the installation of girders safely and on schedule, while limiting interruption to ground and Calgary Airport air traffic as little as possible.

The remaining girders for the Airport Trail and Barlow intersection are scheduled for mid-April and we look forward to continuing to collaborate with the following partners on this install.

Owner – City of Calgary

Construction Manager - PCL Construction

Precast Fabricator – Eagle Builders

Check out this great arial video of the
Lowes Distribution Centre from the Highfield Group here.

Lowes Distribution Centre

Highplains Building 5

Project Duration: October – December 2020

Highway 566 & Lowes Rd Balzac AB

Con-Steel installed 418 insulated precast wall panels at the Highplains 5 Warehouse (Lowes Distribution Centre) over a span of 10 weeks. From the start, the 1.2 million sq ft warehouse project was intended to be built with an expedited schedule in mind. Through careful planning and coordination with Clark Builders and Knelsen Precast, Con-Steel was able to complete our scope of the project within a 2-month time frame and with 0 incidents or injuries.

 

Construction Manager – Clark Builders

Precast Fabricator – Knelsen Precast

Calgary Farmers Market

Building A & L

Project Duration: February – April 2021

Greenwich Village

 

Located in the Greenwich Village on the West side of Calgary, the new Calgary Farmers Market encompasses a unique building design and the architectural brick inlay panels will be sure to make this building stand out as a landmark project for years to come. A total of 220 insulated wall panels for Building A (brick inlay precast design) and 38 panels (architectural base) for Building L have been installed by Con-Steel.

 

Although, the building design and geometry modified the crews initial installation sequence, our talented and professional team ensured the project was completed on time and without any safety incidents.

Owner – Melcor Development

Construction Manager - Clark Builders

Precast Fabricator – Knelsen Precast

Learn more about the new Calgary Farmer’s Market and construction updates here.

"As Construction Director I witnessed the growth and development of the key individuals in the Con-Steel group when they were Construction employees with one of the most recognized precast concrete group in Canada. The experience and maturity of the group was evident in Con-Steel’s performance during the Palliser Panel Removal project. The planning of activities resulted in a very safe, efficient project for all participants."

— Wilf Mckee, Construction Director - P.Eng

Palliser One Reclad

Project Duration: May 2019 - June 2020

125 9 Ave SE Calgary AB

 

Palliser One has been a landmark in the city, standing beside the Calgary Tower and holding the corner of 9th Ave and Macleod Trail south since 1967. Typical of the era, Palliser One was clad in precast concrete panels that had reached their life cycle limitations. At 27 stories tall and a typical floor of +/- 16,500 sq. ft. the Palliser One building has substantial external façade. Aspen Properties was taking measures to maintain the building façade and requested a complete removal and re-clad of the structure - one of the first large scale projects of this nature in Calgary.

 

Challenges to this project were swingstage/ access requirements and initial panel removal with a mobile crane to facilitate use of the tower crane. Con-Steel worked closely with Ellisdon to overcome these challenges. Over 1400 precast panels were removed and over 8000 hours worked with 0 lost time or injury incidents. Con-Steel was able to complete this project ahead of the anticipated schedule.

Affiliated Managers: EllisDon and Entuitive

"As Construction Director I witnessed the growth and development of the key individuals in the Con-Steel group when they were Construction employees with one of the most recognized precast concrete group in Canada. The experience and maturity of the group was evident in Con-Steel’s performance during the Palliser Panel Removal project. The planning of activities resulted in a very safe, efficient project for all participants."

— Wilf Mckee, Construction Director - P.Eng

Enmax Substations

Project Duration: September - December 2019

Five Locations Around Calgary

 

With the growth and expansion of Calgary, Enmax power sought to build five new substations around the city to help deliver safe reliable power to Calgarians. Con-Steel took this project on and was challenged by the tight jobsite parameters and expedited schedule. 152 insulated panels were installed for five buildings in five different locations. Over 1600 hours were worked with zero lost time or injury incidents.

Affiliated Managers: Kassian Dyck & Associates and Graham Construction

"Having worked with the Con-Steel team for several years I can attest that they always bring an

exceptional level of expertise and professionalism to each project."

— Chad Hendry, Heavy Lift Crane Supervisor - Mammoet Canada West

Fehr Carwash

Project Duration: May 2020

15402 101 St Grande Prairie AB

 

This project involved a three bay carwash with structural precast panels. 190 panels were erected in six days with braced design. This project involved 745 hours worked with zero injury or lost time incidents.

Affiliated Managers: Hiway Steel Structures

and BVP Design

Ready For A Consultation?

bottom of page