Projects
Construction Manager - Ledcor Group
Fabricators:
68th St Logistics – Knelsen Sand & Gravel
Point Trotter - Proform Concrete
68th Street Logistics & Point Trotter
Project Duration: February - October 2023
9620 68 St SE & 7121 108 Ave SE
The first project we started installation on here is the Rise at Point Trotter, which is comprised of two 105,000 sq footage warehouses that will be designated as commercial condominium bays.
Our second project in this area is the 68th Street Logistics Warehouses, these are open concept style warehouses designed for distribution and transport logistics.
Each building has approximately 350 precast wall panels that are strapped to the steel as a part of the building envelope and will take approximately 2-3 months for installation.
In total Con-Steel will be working in this area erecting four separate buildings and installing over 1200 precast concrete wall panels for a duration of approximately 10 months.
BMO Centre Expansion
Project Duration: December 2021 - January 2024
20 Roundup Way SE Calgary
At over one million square feet, the new BMO Centre will be the newest, largest, and most modern convention centre in Western Canada. Con-Steel installed 184 architectural brick inlay wall panels and 236 captones as part of this massive expansion project. Working in the downtown core was often challenging regarding site access and required a strategic plan. The installation of the grand staircase in particular created some difficulties along the way and required a collaborative approach between the manufacturer, engineers and install team to meet the tight tolerances and acquire precise alignment. This architecturally inspired building will accommodate and elevate major, year-round events and create memorable guest experiences.
Owner - Calgary Stampede
Construction Manager - PCL
Precast Fabricator - Knelsen Sand & Gravel
Amazon Violin Warehouse
& Distribution Centre
Project Duration: November 2021 - June 2022
68th St and 104 ave SE
At an impressive 1 million square feet, the Amazon Violin Warehouse & Distribution Centre located in SE Calgary is the largest project (square footage) that our crew has provided field installation services for to date. Over a period of 8 months we installed 666 load bearing precast concrete wall panels. This project required a 250 ton crane to lift the 55,000 lbs panels. Milestone scheduling was a top priority based on a tight timeline as we worked towards the owners targeted opening date. We were also responsible for international equipment procurement, resourcing bracing and screw anchors required for the install. As the scope of our work continues to expand we will continue to aspire to fulfill the wide range of our clients needs.
Owner - Amazon
Construction Manager - Clark Buidlers
Precast Fabricator: Knelsen Sand & Gravel
Owner - Telus
Construction Manager - Delnor Construction
Telus Len Werry Panel Removal
Project Duration: October 2022 - January 2023
7 Ave and 2 St SW Calgary
As the downtown Calgary skyline evolves and precast clad building envelopes have reached their lifecycle, Con-Steel is here to manage and execute these removal and remediation projects.
Our team successfully removed 189 precast panels from the 15th to the 17th floor of the Telus Len Werry building over a bustling LRT station and where the panels were set under a cantilevered roof slab.
Our team of experienced, skilled precast removal experts collaboratively worked with all contractors, engineers and required vendors to ensure the project was completed efficiently with the highest safety standards.